Customer:
Cork University Hospital
Site Type:
Hospital Extension 12000M2.
Coverage Requirement:
Full Multi-operator / Multi technology DAS inbuilding solution.
Building construction Phase:
Mid build / 2nd fix
Project Description:
Design, installation and commissioning and full handover of an in-building repeater solution to provide full coverage, all mobile technologies (G900 U900, & U2100). Full compliance to Health & Safety and welfare at work act – 2005.
Client: Cork University Hospital
Project Duration: 6 months
Project management: Fully project managed by Surecom
Responsibilities:
-
Role PSDS
-
Responsibilities: Solution Design (TEMs walk test, iBuildnet design coverage predictions, Antenna location verification – CW testing, BOM, MNO Design approval.)
-
-
Role PSCS
-
Responsibilities: (BOM logistics-onsite), Main Contractor liaison and communication– site in construction phase, H&S compliance supporting site main contractor rules and co-operation to allow for working alongside other companies on site, Sample installation of the cable and antenna to support and agree methodology.
-
Installation of solution to the design specifications (Cable [Co-axial-leaky feeder], Fibre & power), antennae, Radio units). Inclusive of “as build” handover.
-
Commissioning – Cable testing (Sitemaster & fibre), commissioning & optimisation, handover - walk and coverage
-
Project management – Daily & weekly on-site meeting, weekly & monthly checkpoint & highlight reporting-6.
-
-
Team
-
Project Manager
-
Design Engineer X 1
-
Installation team of 6 men
-
Health and Safety Officer
-